1
|
- Zion Hill
- Pineville, Louisiana 71360
- The vision of this ministry is to exhibit and excel in these
principles..
- Worship - Evangelism - Ministry - Discipleship - Fellowship
|
|
2
|
- Yesterday’s Worship Center (Multiple Locations)
|
|
3
|
- To bless and praise God in the process
- To accomplish the building of the new edifice in multiple phases and
within the construction time frame as indicated by the project architect
- To be mindful of this ministry’s history of paying its debt ahead of
schedule
|
|
4
|
- Worship, Fellowship, and Multipurpose Facilities
- PHASE I – Family Worship Center
- Break Ground March 2001 pending geotectonic (soil) report
- PHASE II – Family Life Center
- Additional Phases to be planned as this ministry grows in Jesus Name
|
|
5
|
- Paid around $500,000 for property and design documents
- Will utilize some endowment funds and 1.6 million loan from a local bank
to begin construction, PHASE I
- Continue to be a tithing ministry
- Continue to give above and beyond for the building of God’s House (Zion)
on the hill
|
|
6
|
- By the Grace of God and
- G - God
- R - Rewards
- O - Our
- W - Worship
- T - To
- H - Him
- GROWTH - “And I, if I be lifted up from the earth, will draw all men
unto me.” John 12:32 KJV
|
|
7
|
- General Requirements (job superintendent, job office, surveying, lab
testing, etc.) $220,000 - 250,000
- Site work (clearing, grading, utilities, building pad, parking lot base)
$135,000 - 165,000 …1-2 months
- Concrete (formwork, reinforcing steel, plumbing and electrical stub out)
$120,00 - 140,000 …1-2 months
- Steel (pre-engineered rigid steel frames, erection) $275,00 - 300,000
…1-2 months
- Framing (metal stud exterior and interior walls, mechanical contractor
begin) $100,000 - 120,000 …2-3 months
- Masonry (brick and stucco exterior, metal windows and doors set) $130,000
- 150,000 …1-2 months
|
|
8
|
- Interior (drywall, suspended ceilings, glass, plumbing, electrical &
mechanical rough-in) $175,000 - 200,000 …2-3 months
- Finishes (floor covering, painting, cabinets, pews, audio/video, etc.) $250,000
- 300,000 …2-3 months
- Exterior (parking lot pavement, striping, lighting) $100,00 - 125,000
…1-2 months
- Punch List (final inspection, certificate of occupancy from the city) N/A
…1-2 months
- Total Time -10 - 14 months (January 2002 - May 2002)
- Total Cost Estimate - $1,505,000 - 1,750,000
|
|
9
|
- Pray for completion on schedule
- Pray cost savings be applied to Phase II
- Prepare for the move into the new facility (celebration Worship
experience to God)
- Give thanks and bless the house of the Lord in Jesus Name. Amen.
|
|